For the same amount of work …
CBSE, JEE, NEET, CUET
Question Bank, Mock Tests, Exam Papers
NCERT Solutions, Sample Papers, Notes, Videos
Related Questions
Posted by Hari Anand 2 weeks, 1 day ago
- 0 answers
Posted by Parinith Gowda Ms 10 months, 4 weeks ago
- 0 answers
Posted by Kanika . 2 days, 11 hours ago
- 1 answers
Posted by Sahil Sahil 10 months, 4 weeks ago
- 2 answers
Posted by Parinith Gowda Ms 10 months, 4 weeks ago
- 1 answers
Posted by Vanshika Bhatnagar 10 months, 4 weeks ago
- 2 answers
myCBSEguide
Trusted by 1 Crore+ Students
Test Generator
Create papers online. It's FREE.
CUET Mock Tests
75,000+ questions to practice only on myCBSEguide app
Rajeev Malhotra 7 years, 7 months ago
let a boy takes x hours to complete the work. So an adult will take x-6 hours to complete the work. So work done by boy in 1 hour= 1/x and work done by adult in 1 hour = 1/x-6
They complete the work in 13 hours and 20 minutes. So they complete the work in 40/3 hours. So work done by both in 1 hour = 3/40
1/x+1/x−6=3/40
2x−6/x(x−6)=3/40
By cross multiplication, we get
80x−240=3x2−18x
3x2−98x+240=0
3x2−90x−8x+240=0
3x(x−30)−8(x−30)=0
(x−30)(3x−8)=0
x=30or8/3
So x = 30. So a boy can alone complete work in 30 hours.