Tfc cost of producing 100 unit …

CBSE, JEE, NEET, CUET
Question Bank, Mock Tests, Exam Papers
NCERT Solutions, Sample Papers, Notes, Videos
Posted by Ayush Raj Singh 6 years, 7 months ago
- 1 answers
Related Questions
Posted by Shruti Singh 1 year, 5 months ago
- 0 answers
Posted by Naman Jain 1 year, 4 months ago
- 1 answers
Posted by Niyati Garg 1 year, 4 months ago
- 0 answers
Posted by Rijum Karlo 1 year, 4 months ago
- 0 answers
Posted by Mehar Ansari 1 year, 5 months ago
- 0 answers
Posted by Dipika Sharma 1 year, 4 months ago
- 0 answers
Posted by Nandita Sharma 1 year, 5 months ago
- 1 answers

myCBSEguide
Trusted by 1 Crore+ Students

Test Generator
Create papers online. It's FREE.

CUET Mock Tests
75,000+ questions to practice only on myCBSEguide app
myCBSEguide
Gaurav Seth 6 years, 7 months ago
Given -
Quantity Produced or Output = 100 units
Total Fixed Cost = Rs. 30
Average Variable Cost = Rs. 3
Average Variable Cost = Total Variable Cost/Output
⇒ 3 = Total Variable Cost/100
⇒ Total Variable Cost = 100*3
= Rs. 300
Total Variable Cost = Total Cost - Total Fixed Cost
⇒ 300 = Total Cost - 30
⇒ Total Cost = 300 + 30
⇒ Total Cost = Rs. 330
So, Total cost is Rs. 330
2Thank You